1. A power control system in a data center, comprising:

  • at least one physical server;

    at least one virtual server coupled to the at least one physical server;

    at least two loads, each load having a local power controller in communication with a power model; and

    a server/power controller to control task loading on the at least one physical server through adjustment of tasks on the at least one virtual server, the server power controller receiving inputs from the power model about status of the loads and power consumption including a predictability rating of power consumption of a particular customer where the predictability rating affects cost of power to the particular customer, and quality of service requirements for that customer selected based upon a business input, and generating signals to arrange processing tasks to meet power saving targets.

View all claims
  • 6 Assignments
Timeline View
Assignment View
    ×
    ×