System and method for control of power distribution

  • US 9,917,436 B2
  • Filed: 10/30/2007
  • Issued: 03/13/2018
  • Est. Priority Date: 10/30/2007
  • Status: Active Grant
First Claim
Patent Images

1. A system for controlling a multi-feed power distribution network, the network including a first network sector that includes a first plurality of devices distributed along a first feeder connected to a first power source via a plurality of nodes and one or more other network sectors that each include a plurality of devices distributed along feeders connected to power sources via a plurality of other nodes, the system comprising:

  • a first substation controller and one or more other substation controllers, wherein the first substation controller is configured to control operation of each of the first plurality of devices in the first network sector and exchange data with the one or more other substation controllers, and the one or more other substation controllers are configured to control operation of each of the plurality of devices in the one or more other network sectors; and

    a control application accessible by each substation controller and configured to store a variable size data array of topology data representing each of the first substation controller, the one or more other substation controllers, the first plurality of devices and the plurality of devices distributed along feeders, the control application being executed by either the first substation controller or the one or more other substation controllers to isolate one or more faults by controlling topology of the network based on the topology data and to restore power dynamically based on requesting and receiving power availability information and circuit capacity restrictions, wherein the requesting and receiving power availability information and circuit capacity restrictions is performed according to a priority list with a priority setting for each substation controller and wherein to isolate the one or more faults comprises opening one or more last active nodes before the one or more faults and opening all remaining active nodes immediately following the one or more faults and wherein to isolate the one or more faults further comprises opening one or more selected phases of one or more of a plurality of switches surrounding the faulted segment and wherein communication between the first substation controller and the one or more other substation controllers comprises requesting restoration of power to one or more isolated phases in the one or more isolated segments and wherein communication between the first substation controller and the one or more other substation controllers further comprises receiving power restoration capability from each of the one or more other substation controllers.

View all claims
  • 2 Assignments