External heat preservation cement decoration panel with flexible sealing joint and mounting and leveling method of panel

External heat preservation cement decoration panel with flexible sealing joint and mounting and leveling method of panel

CN
  • CN 105,715,006 A
  • Filed: 02/29/2016
  • Published: 06/29/2016
  • Est. Priority Date: 02/29/2016
  • Status: Active Grant
First Claim
Patent Images

1. for the decoration of cement panel of external wall outer insulation and an installation leveling method thereof, joining metal or nonmetal net in it is characterized in that, lateral surface is prefabricated with 3 D stereo decorative pattern;

  • Medial surface is plane or four limits height, middle low flute profile;

    Upper surface sets logical length convex key, and arranges metal hanger at a certain distance, and lower surface and both sides end face set groove;

    When the construction of described decoration of cement panel assembles, horizontal joint way is;

    a upper row plate lower surface is just to being superimposed on next row plate upper surface, and the logical length convex key of next row plate upper surface embeds in a upper row plate lower surface groove, constitutes sunk key formula seam;

    Perps way is;

    first fill fluid sealant in the groove of plate side end face respectively, and plate is just to being close to and after anchor and position, then the undercut formed at two grooves is inserted into metal or plastic leakage plate, constitutes Concealed groove type flexible sealing seam;

    The plate face of plate is parallel to decoration of cement panel plate face, and when perps is straight joint, upper lower plugboard overlaps downstream;

    Described decoration of cement panel is by metal hanger and adopts Special anchor bolt and plastic mattress pipe to install the upper wall of anchoring, and base course wall is withstood in plastic mattress pipe one end, and the other end withstands metal hanger;

    Described decoration of cement panel in a pre-installation, is adopt following methods and step to carry out levelling to base course wall;

    (1) bullet row plate frame barBullet row plate frame bar on base course wall, and mark the anchor connection point position line;

    (2) levelling benchmark point is setAt base course wall both sides of the edge place along vertically arranging expansion anchor to each uniform laying one, vertically it is not more than to spacing and draws together chi length;

    Two arrange expansion anchors in level to being mutually aligned, and stagger with anchor connection point position;

    The holdfast of expansion anchor exposes metope suitable length, releases levelling benchmark point with instrument or specific purpose tool on each holdfast;

    (3) benchmark ash cake is setMetal horizontally it is uniformly arranged by frame at each expansion anchor height and position, metal by support and is horizontally placed at forming by bar on the cantilever of support both sides by frame, holdfast central point by bar upper surface Yu expansion anchor is positioned at sustained height, it is connected with support both sides cantilever screw by bar two ends, cantilever has elongated hole, when unclamping screw, pass through the distance of elongated hole adjustment and base course wall by bar;

    Metal is fixed on base course wall by frame nail or crab-bolt;

    Metal leans on frame vertical to being mutually aligned, and aligns with anchor connection point;

    Metal is not more than to spacing by frame level draws together chi length;

    According to the levelling benchmark point on base course wall both sides holdfasts, with instrument or specific purpose tool correct each metal by frame by bar position, level is positioned at same straight line to each row'"'"'s metal by being adjusted to by bar outward flange of frame, and aligns with the line of both sides levelling benchmark point;

    Vertical to each two metal by smearing 1-2 benchmark ash cake between frame, adopt long chi of directly drawing together to be close to upper and lower metal and draw together flat by the bar that leans on of frame by benchmark ash cake;

    Benchmark ash cake vertical to level to proper alignment, be mutually aligned, the central point alignment anchor connection point of benchmark ash cake;

    (4) levelling ash cake is smearedMetal is removed by frame, smears levelling ash cake for foundation in all the other each anchor connection point positions with benchmark ash cake, then it is levelling to complete base course wall according to levelling ash cake;

    The central point alignment anchor connection point of levelling ash cake.

View all claims
    ×
    ×