The construction method of shield piping lane

The construction method of shield piping lane

  • CN 107,514,262 A
  • Filed: 08/02/2017
  • Published: 12/26/2017
  • Est. Priority Date: 08/02/2017
  • Status: Active Application
First Claim
Patent Images

1. a kind of construction method of shield piping lane, it is characterised in that comprise the following steps:

  • Construction shield well;

    Shield machine is provided, by the shield machine in the shield well, and the design from the shield well in along piping laneRoute carries out tunneling construction;

    In segment assembly in the tunnel for excavating formation during the shield machine tunnels;

    Along the design route interval installation technicses well of piping lane, the process well of constructing;

    When at shield machine tunneling construction to the process well, the completion if process well has been constructed, by the shield machine from instituteState and tunneling construction forward is passed through and continued at process well, and will be close to the section of jurisdiction at the process well with the process well in successionConnect;

    If the process well is not constructed, the shield machine tunneling construction is passed through at the process well and at the process wellSegment assembly in tunnel.