Method and system for restarting a project management system scheduling engine based on user input of contractual start/ finish data

Method and system for restarting a project management system scheduling engine based on user input of contractual start/ finish data

  • CN 1,728,168 A
  • Filed: 06/15/2005
  • Published: 02/01/2006
  • Est. Priority Date: 06/15/2004
  • Status: Active Application
First Claim
Patent Images

1. the user based on contract item execution data imports management project to manage the method for program, comprising:

  • Reception is about the data dispatching of project;

    Each the data dispatching of project management program based on generating comprising of receiving one or more project major events of being used to have project generates the first project management program;

    Reception is used to specify the contract Close Date of project major event;

    AndIf the project management program that is used to specify the generation of project major event lags behind the contract Close Date of technical routine major event, then restart the project management program at the end of contract Close Date of the project major event that is used to specify;

    AndBased on the contract Close Date of the project major event that is used to specify, be created on the revision project management program of any project major event that arrives after the project major event that is used to specify.