1. A method of conducting operations to an offshore field from multiple separated drill centers, the method using a floating vessel having a turret-mounted mooring element and further having a workstation horizontally spaced apart from the mooring element, comprising the steps of:

  • a) locating the mooring element approximately over a first mooring element location;

    (b) limiting the horizontal movement of the mooring element using a plurality of mooring lines extending from the mooring element;

    (c) allowing the vessel to weathervane such that the workstation is substantially vertically aligned over a first drill center associated with the first mooring element location;

    (d) temporarily restraining the weathervaning of the vessel;

    (e) using the workstation to conduct operations in at least one well from the first drill center to the field;

    (f) removing the weathervaning restraint while continuing to limit horizontal movement of the mooring element and repeating steps (c), (d) and (e) for one or more additional drill centers associated with the first mooring element location.

View all claims